Alaska was laid down on 17.12.41 and Guam was laid down on 02.02.42. Your POD of late 1941 is probably early enough to have both ships cancelled and have a pair of Essexes laid down on the same dates.
@EwenS do you agree?
IOTL New York Shibuilding Corporation built one Essex. She was CV-20 Bennington, laid down on 15.12.42, launched on 20.02.44 and completed on 06.08.44. So she was launched 14 months after she was laid down and completed 20 months after she was laid down.
On that basis:
- An Essex built instead of Alaska would have been completed in August 1943 - Alaska was completed on 17.06.44.
- An Essex built instead of Guam would have been completed in October 1943 - Guam was completed on 17.09.44.
- An Essex built instead of Hawaii would have been completed in August 1945 - Hawaii was launched on 03.11.45.
However:
- Alaska and Guam were launched on 15.08.43 and 12.11.43 respectively.
- Hawaii was laid down on 20.12.43
- So it looks like Hawaii was laid down on the slipway vacated by Guam.
- Bennington was launched 14 months after she was laid down.
- On that basis:
- The Essex built instead of Alaska would have been launched in February 1943.
- The Essex built instead of Guam would have been launched in April 1943.
- That would have allowed the Essex built instead of Hawaii to be laid down in May 1943 instead of December 1943.
- Advancing her completion from August 1945 to January 1945.
Although the abundance of Essex class aircraft carriers means that they decommission in 1947, don't receive the SCB.27 & SCB.125 refits, are re-designated aircraft transports (AVT) on 15.05.59 and in common with the other 5 Essex class AVTs are struck from the naval register 1964-69 and sold for scrap 1966-73.
Firstly a correction. Bennington was the first of
5 Essex class laid down at the
New York (Brooklyn) Navy Yard. (NYNY). 3 were completed and 2 suspended at the end of WW2.
The Alaskas were ordered from
New York Shipbuilding Corp, Camden, New York, (NYSB) a commercial company. It specialised in building cruisers, of which the Alaskas were the largest. It
never built an Essex. It did convert / build the CV-3 Saratoga and the 9 Independence class CVL as well as the two later Saipans (again based on a cruiser hull). Its next carrier was CVA-63 Kitty Hawk.
CV10 to CV-12 were ordered in May 1940 followed by CV-13 to CV-19 on 16 Aug 1940 (Friedman - US Carriers). The lead yard for the Essex programme was Newport News with Bethlehem Quincy close behind. But it was April 1941 before the design was finalised and the lead ship could be laid down at Newport News with CV-16 at Bethlehem following in July.
As for build times, be careful. Those actually achieved in wartime were not what was being predicted in 1941. In Nov / Dec 1941 an Essex was predicted to take 33-47 months to build. Those lengthy build times were what was spurring FDR to want the CVL programme that the USN only reluctantly accepted in Jan 1942.
Build times for the wartime completions ranged from 14 months for CV-13 Franklin (Newport News) to 27 months for CV-39 Lake Champlain (Norfolk Navy Yard - 7 months longer than their first Essex). The averages in the 5 yards involved ranged from 17 months (Newport News over their 8 completions) to 24 months (Norfolk Navy Yard over their 2 completions). So quite a bit of variation for multiple reasons.
CV-20 Bennington & CV-21 Boxer were ordered post PH as a part of a quick expansion but not laid down until Dec 1942 & Sept 1943. The next order arose in Aug 1942 (10 ships), following the big Pacific carrier battles earlier in the year. A further order of 3 was made in 1943 to cover expected attrition.
So what actually happened was something extraordinary that was not forseen in 1941 which is the POD for this exercise.
Due to a lack of capacity at BuShips, much of the design of the Alaskas was carried out by NYSB and was not completed and signed off by BuShips until May 1941.
So some questions:-
1. Why does the USN in mid / late 1941 decide it needs more than the 11 Essex class already on order? (remember the post PH response was to order only 2 more and embark on FDR's CVL proposal to get more carriers quickly. Remembering that at that stage an Essex was expected to take 33 months minimum to complete.)
2. How quickly can NYSB actually build an Essex, never having built one before? Part of that is the urgency perceived in Spring 1942 and the priorities for resources.
3. If the Alaskas are to be converted to carriers, how quickly can they be redesigned? Remembering that NYSB had the CVL programme on its plate at the time, for which they were responsible for much of the redesign work. And that programme was FDR's pet project.
4. How badly were the Alaskas affected by the 1942 steel shortage? (that was what led to the suspension of the 5 Montanas and 4 Alaskas in 1942). What were the priorities in allocating steel? Lot of escorts and then landing craft being ordered in 1942.
So I really can't see the USN dropping the Alaskas for more Essex in 1941. They felt that they had enough already. Otherwise why not order more than 2 in Dec 1941?
Converting the Alaskas to carriers is even more of a waste of resources. Historical evidence, even then, was that a ship designed from the keel up as a carrier, made for a more efficient carrier, than some battlecruiser / cruiser conversion except where needs must (Independence class).
If you really must have more carriers ordered in 1941, replacing the Alaskas with more Essex is the route to go, subject to one proviso. Did NYSB in 1941 have the facilities to build 2 Essex simultaneously? While they built Saratoga, which suggests the availibility of 1 slip of the appropriate size, did they have 2?